Title:
|
Contract 27-17 was awarded to Northeast Asphalt, Inc for the 2017 Water Treatment Facility Hardscapes Repairs project in the amount of $88,987 with a contingency of $13,000. No change orders were issued. Payments issued to date total $84,537.41. Request to issue the final contract payment of $4,449.34
|