Title:
|
Request approval of Contract Amendment/Change Order No. 1 to contract 39-17 for Unit E-17 Miscellaneous Concrete & Street Excavation Repairs to increase for additional street patches from previous years' water main breaks, lead service line replacements, curb box repairs and valve repairs in the amount of $55,000.00 resulting in no change to contingency. Overall contract increased from $530,676.25 to $585,676.25. NOTE: This contract amendment is contingent upon approval of a $55,000 Budget Adjustment which is a separate action item on this Committee Agenda.
|