File #: 17-1023    Version: 1 Name:
Type: Presentation Status: Filed
File created: 7/5/2017 In control: Finance Committee
On agenda: 7/10/2017 Final action: 7/10/2017
Title: Contract 13-17 was awarded to Weinert Roofing, Inc. for the 2017 MSB Roof Repairs project in the amount of $178,245 with a contingency of $17,755. One change order was issued in the amount of $6,053. Payments issued to date total $168,857.75. Request to issue the final contract payment of $15,440.25.
Attachments: 1. 2017 MSB Roof Repairs Final Payment.pdf

Title

Contract 13-17 was awarded to Weinert Roofing, Inc. for the 2017 MSB Roof Repairs project in the amount of $178,245 with a contingency of $17,755.  One change order was issued in the amount of $6,053.  Payments issued to date total $168,857.75.  Request to issue the final contract payment of $15,440.25.