File #: 17-551    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 4/19/2017 In control: Utilities Committee
On agenda: 4/25/2017 Final action: 4/25/2017
Title: Change Orders #1 and #2 to August Winter & Sons Inc. contract as part of the Bar Screen #1 Channel Butterfly Valve Rebuild Project for structural steel repairs and welding totaling $12,000 resulting in a decrease in contingency from $13,750 to $1,750. No change to overall contract amount.
Attachments: 1. Bar Screen #1 Valve Rebuild Change Order to AWS.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Change Orders #1 and #2 to August Winter & Sons Inc. contract as part of the Bar Screen #1 Channel Butterfly Valve Rebuild Project for structural steel repairs and welding totaling $12,000 resulting in a decrease in contingency from $13,750 to $1,750. No change to overall contract amount.