File #: 17-466    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 4/6/2017 In control: Finance Committee
On agenda: 4/11/2017 Final action: 4/19/2017
Title: Request to approve Contract Amendment/Change Order No. 1 to contract 9-17 for Unit U-17 Sewer and Water Reconstruction No.2 to increase for additional sanitary, storm, water and traffic items added to scope of work by the City in the amount of $64,082 resulting in a decrease to contingency from $122,500 to $74,003. Overall contract increased from 2,456,936 to 2,472,520.
Attachments: 1. Unit U-15 Contract Amendment-Change Order No.1.pdf

Title

Request to approve Contract Amendment/Change Order No. 1 to contract 9-17 for Unit U-17 Sewer and Water Reconstruction No.2 to increase for additional sanitary, storm, water and traffic items added to scope of work by the City in the amount of $64,082 resulting in a decrease to contingency from $122,500 to $74,003.  Overall contract increased from 2,456,936 to 2,472,520.