File #: 16-1892    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 12/6/2016 In control: Finance Committee
On agenda: 12/13/2016 Final action: 12/21/2016
Title: Request to approve Change Order #1 to contract 50-16 for Erb Park and Pool renovation project for a separated recirculation system of slides in the amount of $130,590.99 resulting in a decrease of the contingency from $613,048 to $482,457.01. No change to the overall contract amount.
Attachments: 1. 2016 Erb Pool Construction Change Order #1.pdf

Title

Request to approve Change Order #1 to contract 50-16 for Erb Park and Pool renovation project for a separated recirculation system of slides in the amount of $130,590.99 resulting in a decrease of the contingency from $613,048 to $482,457.01.  No change to the overall contract amount.