Title:
|
Approve Contract Amendment and Change Order No. 1 to contract 33-16 for Unit X-16 Sewer & Water Reconstruction No.2 for additional stone backfill material required on Glendale Avenue due to extremely unstable soil conditions encountered during construction in the amount of $60,000 resulting in a decrease to contingency from $46,000 to $1,000. Overall contract increased from $1,721,570 to 1,736,570.
|