File #: 16-1401    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 9/8/2016 In control: Finance Committee
On agenda: 9/13/2016 Final action: 9/21/2016
Title: Approve Contract Amendment and Change Order No. 1 to contract 33-16 for Unit X-16 Sewer & Water Reconstruction No.2 for additional stone backfill material required on Glendale Avenue due to extremely unstable soil conditions encountered during construction in the amount of $60,000 resulting in a decrease to contingency from $46,000 to $1,000. Overall contract increased from $1,721,570 to 1,736,570.
Attachments: 1. Contract Amendment and Change Order No.1 Unit X-16.pdf

Title

Approve Contract Amendment and Change Order No. 1 to contract 33-16 for Unit X-16 Sewer & Water Reconstruction No.2 for additional stone backfill material required on Glendale Avenue due to extremely unstable soil conditions encountered during construction in the amount of $60,000 resulting in a decrease to contingency from $46,000 to $1,000.  Overall contract increased from $1,721,570 to 1,736,570.