File #: 16-1399    Version: 1 Name:
Type: Presentation Status: Filed
File created: 9/8/2016 In control: Finance Committee
On agenda: 9/13/2016 Final action: 9/13/2016
Title: Change Orders #1, #2, and #3 to August Winter & Sons Inc. contract as part of the AWWTP Digester Improvements Project for contract extension, PLC equipment, and biogas cross-over pipe modification totaling $14,294 resulting in a decrease in contingency from $38,000 to $23,706. No change to overall contract amount.
Attachments: 1. AWWTP Digester Improvements Change Order.pdf

Title

Change Orders #1, #2, and #3 to August Winter & Sons Inc. contract as part of the AWWTP Digester Improvements Project for contract extension, PLC equipment, and biogas cross-over pipe modification totaling $14,294 resulting in a decrease in contingency from $38,000 to $23,706. No change to overall contract amount.