Title: Request to approve Amendment and Change Order No. 2 to contract 26-15 for Unit E-15 Miscellaneous Concrete and Street Excavation Repairs to increase for additional street patches due to water main and inlet reconstruction in the amount of $53,226.11. This contract does not include a contingency. Overall contract increased from $684,800 to $738,026.11.
Attachments: 1. Contract Amendment No2- Unit E-15 Miscellaneous Concrete and Street Excavation Repairs.pdf

Title

Request to approve Amendment and Change Order No. 2 to contract 26-15 for Unit E-15 Miscellaneous Concrete and Street Excavation Repairs to increase for additional street patches due to water main and inlet reconstruction in the amount of $53,226.11.  This contract does not include a contingency.  Overall contract increased from $684,800 to $738,026.11.