Title: Contract 17-15 was awarded to Northeast Asphalt Inc., "Appleton Memorial Park Northwest Parking Lot Renovation" in the amount of $139,760 with a contingency of $27,952. An approved change order totaled $9,912.20. Final contract amount is $149,672.20 with remaining contingency of $18,039.80. Request to issue the final contract payment of $149,672.20.
Attachments: 1. 2015 AMP Northwest Parking lot - Final Pymt.pdf

Title

Contract 17-15 was awarded to Northeast Asphalt Inc., "Appleton Memorial Park Northwest Parking Lot Renovation" in the amount of $139,760 with a contingency of $27,952.  An approved change order totaled $9,912.20.  Final contract amount is $149,672.20 with remaining contingency of $18,039.80.  Request to issue the final contract payment of $149,672.20.