Title: Contract 18-15 was awarded to MCC Inc, "Asphalt roadway Replacements" for the Wastewater Treatment Plant in the amount of $84,163.85 with a contingency of $8,461.85. A positive change orders approved totaled $1,333.10. Final contract amount is $83,280.75 with remaining contingency of $8,461.85. Payments issued to date total $0. Request to issue the final contract payment of $83,280.75.
Attachments: 1. 2015 Wastewater Asphalt Replacement -#1 Final Pymt.pdf

Title

Contract 18-15 was awarded to MCC Inc, "Asphalt roadway Replacements" for the Wastewater Treatment Plant in the amount of $84,163.85 with a contingency of $8,461.85.  A positive change orders approved totaled $1,333.10.  Final contract amount is $83,280.75 with remaining contingency of $8,461.85.  Payments issued to date total $0.  Request to issue the final contract payment of $83,280.75.