Title: Contract 15-14 was awarded to Milbach Construction, "Pierce Park Band Shelter" in the amount of $328,135 with a contingency of $46,744. Change orders approved totals $26,320.64. Final contract amount is $354,455.64 with remaining contingency of $20,423.36. Payments issued to date total $316,382.05. Request to issue the final contract payment of $38,073.59.
Attachments: 1. 2015 Pierce Pavillion Final Pymt.pdf

Title

Contract 15-14 was awarded to Milbach Construction, "Pierce Park Band Shelter" in the amount of $328,135 with a contingency of $46,744.  Change orders approved totals $26,320.64.  Final contract amount is $354,455.64 with remaining contingency of $20,423.36.  Payments issued to date total $316,382.05.  Request to issue the final contract payment of $38,073.59.