File #: 15-1100    Version: 1 Name: Bar Screen Replacement Project Change Order #3
Type: Presentation Status: Action Item
File created: 6/26/2015 In control: Utilities Committee
On agenda: 7/7/2015 Final action: 7/7/2015
Title: Change Order #3 for the Bar Screen Replacement Project to increase, for screen modifications, in the amount of $1,650 resulting in a decrease to contingency from $96,313 to $94,663. Contract price increased from $744,247 to $745,897 (attachment).
Attachments: 1. Bar Screen Replacement Project Change Order #3 (7-7-15).pdf

Title

Change Order #3 for the Bar Screen Replacement Project to increase, for screen modifications, in the amount of $1,650 resulting in a decrease to contingency from $96,313 to $94,663.  Contract price increased from $744,247 to $745,897 (attachment).