Title: Contract 96-21 was awarded to SDS Painting Company for $181,760 for the WWTP L Building Painting Project. Change orders were approved totaling $3,260. Final contract amount is $185,020. Payments issued to date total $175,932. Request final payment of $9,088.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Contract 96-21 was awarded to SDS Painting Company for $181,760 for the WWTP L Building Painting Project. Change orders were approved totaling $3,260.  Final contract amount is $185,020. Payments issued to date total $175,932.  Request final payment of $9,088.