Title:
|
Contract 29-25 was awarded to Kruczek Construction Inc. for $2,312,222.22 with a contingency of $70,000 for W-25 Sewer & Water Reconstruction No. 2. Change orders were approved totaling $300,451. Final contract amount is $2,612,673.22 with a contingency of $70,000. Payments issued to date total $2,489,165.68. Request final payment of $123,433.28.
|