Title:
|
Contract 15-23 was awarded to Staab Construction Corporation for $5,063,000 with a contingency of $759,450 for the Belt Filter Press - Phase 1. Change orders were approved totaling $238,855. Final contract amount is $5,301,855 with a contingency of $520,595. Payments issued to date total $5,270,917. Request final payment of $30,938.
|