Title:
|
Request to approve Change Order #1 for Project Z-23 Water Reconstruction to increase for additional costs in the amount of $335,035.04, resulting in a decrease to contingency from $150,000 to $0, along with the following 2023 budget amendment (2/3 vote of Council required):
Water Fund
Z-23 Water Reconstruction + $185,035.04
X-23 Water Capital Construction - $185,035.04
|