File #: 24-0132    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 2/6/2024 In control: Finance Committee
On agenda: 2/12/2024 Final action: 2/12/2024
Title: Change Orders #12, #13, and #14 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $10,541 resulting in a decrease in contingency from $532,546 to $522,005.
Attachments: 1. 240201_Finance Memo SSB Addtion Miron Change Orders No12-14.pdf

Title

Change Orders #12, #13, and #14 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $10,541 resulting in a decrease in contingency from $532,546 to $522,005.