File #: 18-1109    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 7/19/2018 In control: Finance Committee
On agenda: 7/23/2018 Final action: 8/1/2018
Title: Request to award the Wastewater 2018 Electrical Distribution Upgrades Phase 1 project contract to Miron Construction, Co Inc in the amount of $1,037,026 with a contingency of 10% for a project total not to exceed $1,140,728
Attachments: 1. 2018 Wastewater Electrical Distribution Phase 1 Upgrades.pdf

Title

Request to award the Wastewater 2018 Electrical Distribution Upgrades Phase 1 project contract to Miron Construction, Co Inc in the amount of $1,037,026 with a contingency of 10% for a project total not to exceed $1,140,728