Title:
|
Contract 12-22 was awarded to Milbach Construction for $1,535,058 for City Hall, 5th & 6th Floor Public Areas. Change orders were approved totaling $62,750.02. Final contract amount is $1,597.808.02. Payments issued to date total $1,510,588.50. Request final payment of $83,219.52 ($4,000 subtracted from final payment due to stair riser repair).
|