File #: 23-1493    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 12/7/2023 In control: Finance Committee
On agenda: 12/11/2023 Final action: 12/20/2023
Title: Request to approve Change Order #1 to Scott Lamers Construction, LLC contract 35-23: Unit Y-23 Lead/Galvanized Water Service Replacements to account for additional properties added to the 2023 program totaling $74,193.13 resulting in a decrease in contingency from $99,090 to $24,896.87.
Attachments: 1. Finance Committee Memo Change Order#1 Y23-20231127.pdf

Title

Request to approve Change Order #1 to Scott Lamers Construction, LLC contract 35-23: Unit Y-23 Lead/Galvanized Water Service Replacements to account for additional properties added to the 2023 program totaling $74,193.13 resulting in a decrease in contingency from $99,090 to $24,896.87.