File #: 21-1390    Version: 1 Name:
Type: Presentation Status: Filed
File created: 10/6/2021 In control: Finance Committee
On agenda: 10/11/2021 Final action: 10/11/2021
Title: Change Order No. 2 to contract 17-20, Unit U-19 North Edgewood Estates Lift Station and Force Main Construction, for relocation of gas line and site restoration in the amount of $5,959.66. This change order reduces contingency from $27,500 to $21,540. Overall contract amount remains unchanged.
Attachments: 1. Unit U-19 Change Order No. 2.pdf

Title

Change Order No. 2 to contract 17-20, Unit U-19 North Edgewood Estates Lift Station and Force Main Construction, for relocation of gas line and site restoration in the amount of $5,959.66. This change order reduces contingency from $27,500 to $21,540. Overall contract amount remains unchanged.