Title:
|
Contract 127-20 was awarded to Cardinal Construction for the 2020 MSB Exterior Masonry Improvements project in the amount of $163,462 with a contingency of $16,346. One change order was issued in the amount of $8,523.41 to add additional wall repairs in the Cold Storage Building. Payments to date total $163,386.14. Request to issue the final contract payment of $8,599.27
|