Title
Change Order No. 3 to Contract 12-12 for Unit T-12 Reid Golf Course Ponds/Channel with Ryan Incorporated Central to increase for additional quantities of drain tile, yard drain, sprinkler heads, retaining wall, geoblock, grading and restoration in the amount of $44,123.65 resulting in a decrease to contingency from $71,953.10 to $27,829.45. No change to overall contract amount