File #: 20-0681    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 6/5/2020 In control: Finance Committee
On agenda: 6/8/2020 Final action: 6/17/2020
Title: Request to approve Contract Amendment/Change Order No. 1 to Contract No. 80-19, Unit J-19 Mini-Storm Sewer Construction for the addition of Orchard Blossom Drive rear-yard drains (2) to the scope of work in the amount of $35,000 with no change to contingency. Overall contract increases from $200,000 to $235,000
Attachments: 1. Unit J-19 Change Order No. 1.pdf

Title

Request to approve Contract Amendment/Change Order No. 1 to Contract No. 80-19, Unit J-19 Mini-Storm Sewer Construction for the addition of Orchard Blossom Drive rear-yard drains (2) to the scope of work in the amount of $35,000 with no change to contingency. Overall contract increases from $200,000 to $235,000