File #: 23-0302    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 3/17/2023 In control: Utilities Committee
On agenda: 3/21/2023 Final action: 4/5/2023
Title: Sole Source Engineering Services Contract to McMahon as part of the 2023 Digester Piping and Heat Exchanger Replacement Project in the amount of $85,300 with a 15% contingency of $12,795 for a Project Total not to exceed $98,095.
Attachments: 1. 2023 Digester Piping and Heat Exchanger Replacement Project Sole Source McMahon.pdf

Title

Sole Source Engineering Services Contract to McMahon as part of the 2023 Digester Piping and Heat Exchanger Replacement Project in the amount of $85,300 with a 15% contingency of $12,795 for a Project Total not to exceed $98,095.