File #: 23-0360    Version: 1 Name:
Type: Presentation Status: Filed
File created: 4/6/2023 In control: Finance Committee
On agenda: 4/10/2023 Final action: 4/10/2023
Title: Contract 133-22 was awarded to Staab Construction Corporation for $237,000 with a contingency of $11,850 for WWTP Aeration Tank Repair. Change orders were approved totaling $11,064. Final contract amount is $248,064 with a contingency of $786. Payments issued to date total $243,064. Request final payment of $5,000.

Title

Contract 133-22 was awarded to Staab Construction Corporation for $237,000 with a contingency of $11,850 for WWTP Aeration Tank Repair. Change orders were approved totaling $11,064.  Final contract amount is $248,064 with a contingency of $786.  Payments issued to date total $243,064.  Request final payment of $5,000.