File #: 13-1625    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 11/5/2013 In control: Utilities Committee
On agenda: 11/12/2013 Final action: 11/12/2013
Title: Change Order No. 1 to the AWWTP Aeration Tank Pipe Project with August Winter and Sons for additional labor, piping, fittings and grating that is necessary for the relocation of piping in the amount of $4,130 resulting in a decrease of contingency from $15,900 to $11,770.
Attachments: 1. Aeration Tank Change Order No. 1.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Change Order No. 1 to the AWWTP Aeration Tank Pipe Project with August Winter and Sons for additional labor, piping, fittings and grating that is necessary for the relocation of piping in the amount of $4,130 resulting in a decrease of contingency from $15,900 to $11,770.