File #: 13-1443    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 10/3/2013 In control: Finance Committee
On agenda: 10/23/2013 Final action: 11/6/2013
Title: Approve Contract Amendment and Change Order No. 1 to Contract 22-13 for Unit U-13 Cherryvale Avenue Sanitary, Storm, Water Main, Grading & Graveling with Carl Bowers & Sons Construction Co., Inc. to increase for changes to the size of storm laterals and water services made by the landowner and the addition of a 42” storm sewer to serve areas to the west in the amount of $13,909.00 resulting in no change to contract contingency. Overall Contract Amount to increase from $344,970.00 to $358,879.00.
Attachments: 1. Unit U-13 Contract Amendment - Change Order No.1.pdf
Title
Approve Contract Amendment and Change Order No. 1 to Contract 22-13 for Unit U-13 Cherryvale Avenue Sanitary, Storm, Water Main, Grading & Graveling with Carl Bowers & Sons Construction Co., Inc. to increase for changes to the size of storm laterals and water services made by the landowner and the addition of a 42" storm sewer to serve areas to the west in the amount of $13,909.00 resulting in no change to contract contingency.  Overall Contract Amount to increase from $344,970.00 to $358,879.00.