Title:
|
Change Order No. 1 to contract 82-20, Unit AA-20 Rubyred Bridge Construction, for concrete footing extension and concrete encasement of sanitary sewer in the amount of $2,500. This change order reduces contingency from $61,000 to $58,500. Overall contract amount remains unchanged.
|