File #: 20-1604    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 12/3/2020 In control: Utilities Committee
On agenda: 12/8/2020 Final action: 12/8/2020
Title: Change Order 1, 2, and 3 to Great Lakes Mechanical in the amount of $816 for the OCCT Apparatus Test Project resulting in the construction contract being increased to $122,156 and a decrease in contingency from $12,134 to $11,318.
Attachments: 1. Change Order 1 2 3 OCCT Test Apparatus Project.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Change Order 1, 2, and 3 to Great Lakes Mechanical in the amount of $816 for the OCCT Apparatus Test Project resulting in the construction contract being increased to $122,156 and a decrease in contingency from $12,134 to $11,318.