Title:
|
Contract 61-21 was awarded to Schulze Exteriors, LLC for the 2021 Park Pavilions Roof Replacement Project in the amount of $106,374 with a contingency of $10,000. One change order was issued in the amount of $9,958 to reconfigure downspouts and replace the rotten wood under the shingles. Payments to date total $111,561.45. Request to issue the final contract payment of $4,410.55
|