Title:
|
Contract 33-16 was awarded to Van Straten Construction Co. for $1,675,570 with a contingency of $46,000 for Sewer/Water Reconstruction #2. Change orders were approved totaling $60,000. Final contract amount is $1,735,570 with a contingency of $1,000. Payments issued to date total $1,690,271.62. Request final payment of $39,332.23.
|