File #: 24-1630    Version: 1 Name:
Type: Presentation Status: Filed
File created: 1/2/2025 In control: Finance Committee
On agenda: 1/6/2025 Final action: 1/6/2025
Title: Contract 108-23 was awarded to Southport Engineered Systems, LLC. for the 2023 MSB CEA Shop HVAC Replacement Project in the amount of $664,550 with an 8% contingency of $53,164. Two change orders were issued in the amount of $35,337. Payments to date total $682,389.81. Request final payment of $17,497.19.

Title

Contract 108-23 was awarded to Southport Engineered Systems, LLC. for the 2023 MSB CEA Shop HVAC Replacement Project in the amount of $664,550 with an 8% contingency of $53,164. Two change orders were issued in the amount of $35,337. Payments to date total $682,389.81. Request final payment of $17,497.19.