Request to approve Change Order #1 to the 2019 Fire Station #4 HVAC Upgrades project to Baumgart Mechanical in the amount of $14,147. The overall contract will increase from $61,050 to $75,197 and approve the following 2020 budget adjustment:
Facilities Capital Projects Fund
2020 Fire Station #6 Hardscape Replacement Ph 2 Proj - $14,000
2019 Fire Station #4 HVAC Upgrades Project +$14,000