File #: 20-0661    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 6/4/2020 In control: Finance Committee
On agenda: 6/8/2020 Final action: 6/8/2020
Title: Change Order #7 and #8 to August Winter and Sons contract as part of the 2017 AWWTP Improvements Projects totaling $1,539 resulting in a decrease in contingency from $145,850 to $144,311
Attachments: 1. AWWTP Improvements Change Order No7-8.pdf

Title

Change Order #7 and #8 to August Winter and Sons contract as part of the 2017 AWWTP Improvements Projects totaling $1,539 resulting in a decrease in contingency from $145,850 to $144,311