File #: 17-1681    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 10/19/2017 In control: Municipal Services Committee
On agenda: 10/23/2017 Final action: 11/1/2017
Title: Approve Contract Amendment/Change Order No. 1 to contract 64-17 for Red Ramp Structural Repairs to increase for the repair of an additional 95 square feet of deteriorated structural concrete beam, identified at time of adjacent column repairs in the amount of $22,705.00 resulting in a decrease to contingency from $5,292.00 to $0.00. Overall contract increased from $40,572.00 to $57,985.00.
Attachments: 1. Red Parking Ramp Structural Column Repairs.pdf

Title

Approve Contract Amendment/Change Order No. 1 to contract 64-17 for Red Ramp Structural Repairs to increase for the repair of an additional 95 square feet of deteriorated structural concrete beam, identified at time of adjacent column repairs in the amount of $22,705.00 resulting in a decrease to contingency from $5,292.00 to $0.00.  Overall contract increased from $40,572.00 to $57,985.00.