File #: 24-0077    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 1/18/2024 In control: Utilities Committee
On agenda: 1/23/2024 Final action: 2/7/2024
Title: Award Final Clarifier Tank Underdrain and Tank Drain Rehabilitation Contract to Sabel Mechanical in the amount of $44,411 with 15% contingency of $6,662 for a project total not to exceed $51,073.
Attachments: 1. 240119_Memo_Final Clarifier Underdrain_Rehab Contract_Sabel.pdf

Title

Award Final Clarifier Tank Underdrain and Tank Drain Rehabilitation Contract to Sabel Mechanical in the amount of $44,411 with 15% contingency of $6,662 for a project total not to exceed $51,073.