File #: 24-0013    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 1/3/2024 In control: Finance Committee
On agenda: 1/8/2024 Final action: 1/17/2024
Title: Request to approve Change Order #4 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $176,232.54 resulting in a decrease in contingency from $244,549.71 to $0.00. No change to overall contract amount.
Attachments: 1. H-21 Change Order 4 memo 01-02-2024.pdf, 2. Unit H-21 Change Order No 4.pdf

Title

Request to approve Change Order #4 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $176,232.54 resulting in a decrease in contingency from $244,549.71 to $0.00. No change to overall contract amount.