Title:
|
Request to approve Change Order #4 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $176,232.54 resulting in a decrease in contingency from $244,549.71 to $0.00. No change to overall contract amount.
|