File #: 24-0550    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 5/1/2024 In control: Utilities Committee
On agenda: 5/7/2024 Final action: 5/15/2024
Title: Approval of Sole Source Engineering Services Contract to McMahon as part of the Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project in the amount of $27,000 with a 10% contingency of $2,700 for a total not to exceed $29,700.
Attachments: 1. 240430_SoleSourceAward_McMahon_CO2_Memo.pdf

Title

Approval of Sole Source Engineering Services Contract to McMahon as part of the Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project in the amount of $27,000 with a 10% contingency of $2,700 for a total not to exceed $29,700.