Title: Rankin Street, from 200’ south of Alton Street to College Avenue, be reconstructed with asphalt pavement and curb and gutter. The dimensions of the Rankin Street reconstruction project are as follows: 200’ south of Alton Street - Alton St: New asphalt pavement to be constructed to a width of 25’ from back of curb to back of curb, which is 1’ narrower than the existing street within this portion of the project. Existing on-street parking to remain unchanged within this portion of the project. Alton St - College Ave: New asphalt pavement to be constructed to a width of 31’ from back of curb to back of curb, which is 2’ narrower than the existing street within this portion of the project. Existing on-street parking to remain unchanged within this portion of the project.

Title

Rankin Street, from 200’ south of Alton Street to College Avenue, be reconstructed with asphalt pavement and curb and gutter.  The dimensions of the Rankin Street reconstruction project are as follows:

200’ south of Alton Street - Alton St:  New asphalt pavement to be constructed to a width of 25’ from back of curb to back of curb, which is 1’ narrower than the existing street within this portion of the project.  Existing on-street parking to remain unchanged within this portion of the project.

Alton St - College Ave:  New asphalt pavement to be constructed to a width of 31’ from back of curb to back of curb, which is 2’ narrower than the existing street within this portion of the project.  Existing on-street parking to remain unchanged within this portion of the project.