Title: Contract 17-15 was awarded to Northeast Asphalt, Inc. for $139,760 with a contingency of $27,952 for Appleton Memorial Park Northwest Parking Lot Renovation. Change orders were approved totaling $9,912.20. Final contract amount is $149,672.20 with a contingency of $18,039.80. No payments issued to date. Request final payment of $149,672.20.

Title

Contract 17-15 was awarded to Northeast Asphalt, Inc. for $139,760 with a contingency of $27,952 for Appleton Memorial Park Northwest Parking Lot Renovation.  Change orders were approved totaling $9,912.20. Final contract amount is $149,672.20 with a contingency of $18,039.80.  No payments issued to date.  Request final payment of $149,672.20.