Title:
|
Contract 106-24 was awarded to Sabel Mechanical LLC for $392,100 with a contingency of $58,815 for Channel Aeration Blower Replacement. Change orders were approved totaling $55,593.32. Final contract amount is $447,693.32 with a contingency of $3,221.68. Payments issued to date total $418,580.66. Request final payment of $29,112.66.
|