                                    Title:
                                 | 
				
                                    Contract 47-18 was awarded to the Boldt Company for the 2018 Blue Parking Ramp Demolition project in the amount of $1,998,000 with a contingency of 15%. One deduct change order was issued in the amount of $10,681 bringing the final contract amount to $1,987,319.  Payments to date total $1,809,387.54.  Request to issue the final contract payment of $177,930.96
                                 |