File #: 23-1396    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 11/15/2023 In control: Municipal Services Committee
On agenda: 11/20/2023 Final action: 12/6/2023
Title: Approve the roadway design parameters: Perkins Street, from Prospect Avenue to the RR Tracks (1,480 ft), be reconstructed with concrete pavement and curb and gutter. The details of the proposed Perkins Street reconstruction project are as follows: · New concrete pavement constructed to a width of 31’ from back of curb to back of curb, which is 9’ narrower than the existing street (40’) within this portion of the project. · New 5’ concrete sidewalk, where none currently exists, within the project limits. · Curb extensions (narrowing of the pavement) at Charles St to serve as traffic calming. · Existing on-street parking would be restricted along the east side of Perkins St, within the project limits.

Title

Approve the roadway design parameters: Perkins Street, from Prospect Avenue to the RR Tracks (1,480 ft), be reconstructed with concrete pavement and curb and gutter.  The details of the proposed Perkins Street reconstruction project are as follows:

                     New concrete pavement constructed to a width of 31’ from back of curb to back of curb, which is 9’ narrower than the existing street (40’) within this portion of the project. 

                     New 5’ concrete sidewalk, where none currently exists, within the project limits.

                     Curb extensions (narrowing of the pavement) at Charles St to serve as traffic calming.

                     Existing on-street parking would be restricted along the east side of Perkins St, within the project limits.