Title: Contract 47-25 was awarded to Staab Construction Corp for $353,000 with a contingency of $8,825 for WWTP Removable Wall Storage. Change orders were approved totaling a credit of $9,054. Final contract amount is $343,946 with a contingency of $17,879. Payments issued to date total $317,280.47. Request final payment of $26,665.53.

Title

Contract 47-25 was awarded to Staab Construction Corp for $353,000 with a contingency of $8,825 for WWTP Removable Wall Storage. Change orders were approved totaling a credit of $9,054. Final contract amount is $343,946 with a contingency of $17,879.  Payments issued to date total $317,280.47.  Request final payment of $26,665.53.