File #: 23-0776    Version: 1 Name:
Type: Presentation Status: Filed
File created: 6/22/2023 In control: Finance Committee
On agenda: 6/26/2023 Final action: 6/26/2023
Title: Contract Change Order No. 2 to contract 72-22, Unit H-21 Redundant Raw Water Line for changes in field conditions in the amount of $30,450.29 resulting in a reduction in contingency from $475,000 to $444,549.71. Overall contract amount remains unchanged.
Attachments: 1. Unit H-21 Change Order No 2 rev.pdf

Title

Contract Change Order No. 2 to contract 72-22, Unit H-21 Redundant Raw Water Line for changes in field conditions in the amount of $30,450.29 resulting in a reduction in contingency from $475,000 to $444,549.71. Overall contract amount remains unchanged.