Title:
|
Request to award the Appleton Wastewater Treatment Plant 2025 L-Building HVAC and Receiving Station Upgrades Project contract to August Winter & Sons, Inc. in the amount of $3,969,472 with a 12% contingency of $476,337 for a project total not to exceed $4,445,809 along with the following 2024 to 2025 budget carryover appropriation (2/3 vote of council required):
2024 Primary Clarifier Rebuild CIP - $895,487
2024 Blended Sludge Piping & Hex Rplcmnt CIP - $1,477,693
2024 L-Building HVAC Upgrades CIP - $2,072,629
2025 L-Building HVAC & Receiving Station Upgrades Proj +$4,445,809
|