File #: 19-1188    Version: 1 Name:
Type: Presentation Status: Action Item
File created: 8/7/2019 In control: Finance Committee
On agenda: 8/12/2019 Final action: 8/12/2019
Title: Change Order No. 1 to contract 13-19 for Unit G-19 Leona Street Stormwater Pond for culvert and driveway installation at offsite stockpile location and irrigation of new prairie seeding in the amount of $12,000 resulting in a decrease to contingency from $61,000 to $49,000. No change to overall contract amount.
Attachments: 1. Unit G-19 Change Order No.1.pdf

Title

Change Order No. 1 to contract 13-19 for Unit G-19 Leona Street Stormwater Pond for culvert and driveway installation at offsite stockpile location and irrigation of new prairie seeding in the amount of $12,000 resulting in a decrease to contingency from $61,000 to $49,000. No change to overall contract amount.