Title:
|
Request to approve change order #1 to Kruczek Construction contract 3-26 Unit U-26 Sewer and Water Construction with an increase of $13,510.50 for a new contract total of $370,510.50 resulting in a decrease in contingency from $35,000 to $21,489.50.
|